How to Install the GEM630MCT Meter
Overview
Follow these steps to install and power the GEM630MCT safely and accurately.
Step-by-Step Installation
-
Isolate all power to the circuit before wiring.
-
Mount the meter on a DIN rail inside the consumer unit or cabinet.
Provide supply power (6 A MCB recommended):
-
Live → Terminal LA
-
Neutral → Terminal NA
-
Connect voltage references:
|
Terminal
|
Function
|
Description
|
|---|
|
L1
|
Phase 1 voltage input
|
From same supply as CT L1
|
|
L2
|
Phase 2 voltage input
|
From same supply as CT L2
|
|
L3
|
Phase 3 voltage input
|
From same supply as CT L3
|
|
N
|
Neutral
|
Common return for all phases
|
Phase rotation must match the property’s rotation.
Incorrect rotation produces negative or inconsistent readings.
|
Phase
|
CT White (+)
|
CT Black (–)
|
|---|
|
L1
|
Port 20
|
Port 19
|
|
L2
|
Port 18
|
Port 17
|
|
L3
|
Port 16
|
Port 15 |
-
Power on the meter and confirm display activation.
Notes
-
Never extend or shorten CT cables.
-
All three CTs must correspond exactly with their voltage references (L1 ↔ CT L1, etc.).
-
If incorrect, readings will drift or invert sign.
Related Articles
How to Install the GEM120CT Meter
Overview This guide explains how to wire and mount the GEM120CT correctly to ensure accurate readings. Step-by-Step Installation Isolate power before working on the system. Mount the GEM120CT on a DIN rail in the distribution board. Connect voltage ...
Monitor Your Meter from Portal
Your GivEnergy system uses meter readings to calculate and display energy usage within the app and portal. These readings are generated by the inverter and depend on accurate meter installation and a stable internet connection. Data Calculation in ...
EM115/GEM120 Grid Meter Installation
Arrow always points towards the load CT clamp cables must not be cut down or extended EM115/GEM120 meters come with a split core CT that has a 2m cable The communication cable for the GEM120 uses the same communication terminals as the EM115 ...
Connecting MID Approved Meter to Inverter
In the system, a mid approved meter must be installed to ensure correct monitoring of the grid power. The inverter uses this information to decide whether to charge or discharge the battery. The CT clamp that is connected to the mid approved meter ...
Understanding LoRa Communication Between Inverter and Meter
Overview LoRa (Long Range Radio) enables wireless communication between GivEnergy inverters and energy meters, eliminating the need for hardwired connections over long distances. How It Works The LoRa module in the inverter transmits data to the LoRa ...