How to Install the GEM630MCT Meter

How to Install the GEM630MCT Meter

Overview

Follow these steps to install and power the GEM630MCT safely and accurately.

Step-by-Step Installation

  1. Isolate all power to the circuit before wiring.

  2. Mount the meter on a DIN rail inside the consumer unit or cabinet.

  3. Provide supply power (6 A MCB recommended):

    • Live → Terminal LA

    • Neutral → Terminal NA

  4. Connect voltage references:


Terminal

Function

Description

L1

Phase 1 voltage input

From same supply as CT L1

L2

Phase 2 voltage input

From same supply as CT L2

L3

Phase 3 voltage input

From same supply as CT L3

N

Neutral

Common return for all phases

Phase rotation must match the property’s rotation.
Incorrect rotation produces negative or inconsistent readings.

  1. Install CT clamps:

    • Clamp only the live conductor of each phase.

    • Arrow must face toward the property load.

    • Connect as follows:

Phase

CT White (+)

CT Black (–)

L1

Port 20

Port 19

L2

Port 18

Port 17

L3

Port 16

Port 15

  1. Power on the meter and confirm display activation.

Notes

  • Never extend or shorten CT cables.

  • All three CTs must correspond exactly with their voltage references (L1 ↔ CT L1, etc.).

  • If incorrect, readings will drift or invert sign.

    • Related Articles

    • How to Install the GEM120CT Meter

      Overview This guide explains how to wire and mount the GEM120CT correctly to ensure accurate readings. Step-by-Step Installation Isolate power before working on the system. Mount the GEM120CT on a DIN rail in the distribution board. Connect voltage ...
    • Monitor Your Meter from Portal

      Your GivEnergy system uses meter readings to calculate and display energy usage within the app and portal. These readings are generated by the inverter and depend on accurate meter installation and a stable internet connection. Data Calculation in ...
    • EM115/GEM120 Grid Meter Installation

      Arrow always points towards the load CT clamp cables must not be cut down or extended EM115/GEM120 meters come with a split core CT that has a 2m cable The communication cable for the GEM120 uses the same communication terminals as the EM115 ...
    • Connecting MID Approved Meter to Inverter

      In the system, a mid approved meter must be installed to ensure correct monitoring of the grid power. The inverter uses this information to decide whether to charge or discharge the battery. The CT clamp that is connected to the mid approved meter ...