How to Install the GEM120CT Meter
Overview
This guide explains how to wire and mount the GEM120CT correctly to ensure accurate readings.
Step-by-Step Installation
Isolate power before working on the system.
Mount the GEM120CT on a DIN rail in the distribution board.
Connect voltage references:
Meter Terminal | Description | Cable |
|---|
3 | Neutral (N) | Neutral supply |
4 | Live (L1) | Live grid feed
|
Install CT clamp:
Place around the live cable only (not neutral).
Arrow on clamp must face toward the property load.
Connect CT clamp wires to the bottom of the meter:
Port | Wire | Function |
|---|
1 | White | CT + |
2 | Black | CT – |
Tighten all terminals and ensure the CT clamp is fully closed.
Power on the system and confirm LED activity.
Notes
Related Articles
How to Install the GEM630MCT Meter
Overview Follow these steps to install and power the GEM630MCT safely and accurately. Step-by-Step Installation Isolate all power to the circuit before wiring. Mount the meter on a DIN rail inside the consumer unit or cabinet. Provide supply power (6 ...
EM115/GEM120 Grid Meter Installation
Arrow always points towards the load CT clamp cables must not be cut down or extended EM115/GEM120 meters come with a split core CT that has a 2m cable The communication cable for the GEM120 uses the same communication terminals as the EM115 ...
Monitor Your Meter from Portal
Your GivEnergy system uses meter readings to calculate and display energy usage within the app and portal. These readings are generated by the inverter and depend on accurate meter installation and a stable internet connection. Data Calculation in ...
Connecting MID Approved Meter to Inverter
In the system, a mid approved meter must be installed to ensure correct monitoring of the grid power. The inverter uses this information to decide whether to charge or discharge the battery. The CT clamp that is connected to the mid approved meter ...
Programming the GEM630MCT Meter from ID1 to ID2
Overview Meters can be configured with IDs 1–8. ID 1 monitors the main grid; ID 2 monitors an external PV inverter or device. Steps to Change ID Press and hold ENTER until the password screen appears. Enter password 1000 using arrow buttons ▲ ▼ to ...