This manual provides the full installation, commissioning, and safety guidance for the
GivEnergy Generation 3 String Inverter range, covering the 3.6 kW, 5.0 kW and 6.0 kW
models. It summarises the official Installation Manual and includes all essential installation
requirements, wiring references, safety instructions, commissioning steps, and shutdown
procedures.
Product Overview
The Gen 3 String Inverter converts DC power from solar panels into usable AC power for
the home. When paired with GivEnergy battery systems, excess generation can be stored
and used later. The inverter accepts up to 17 A per PV string and delivers up to 6.0 kW of
output power depending on the model.
Specifications
| Models | 3.6 kW, 5.0 kW, 6.0 kW |
| Dimensions | 583H × 205D × 480W mm |
| Weight | 32 kg |
| Max PV Voltage | 600 V |
| Start-Up Voltage | 90 V (all models) |
| Operating Temperature | -25°C to +60°C |
| Warranty | 12 years |
Box Contents
- String Inverter main unit
- Mounting bracket
- Fixings pack (5 × M6×70 bolts)
- User documentation
Reference: Box contents on page 2 of the manual.
General Installation Requirements
- Installation must be completed by a GivEnergy Approved Installer.
- Store the inverter between 5°C and 60°C prior to installation.
- Do not stack more than 4 units during storage.
- Verify all components match the order specification before installation.
Safety Instructions
- The system contains high voltage even when disconnected. Do not touch internal parts.
- Installers must comply with IEE Wiring Regulations.
- The heat sink becomes hot during operation — avoid contact.
- Only GivEnergy batteries should be used with GivEnergy inverters.
- Reversed DC polarity will cause damage and void warranty.
- Use a minimum of 16mm² tri-rated cables for DC battery connections.
- The inverter must be mounted vertically with all connections at the bottom.
Mounting and Wall Requirements
The mounting bracket must be fixed to a wall at least 100 mm thick. Drill 5 × 80 mm deep
holes and secure the bracket with the provided M6×70 expansion bolts.
- Impact drill
- Flathead and crosshead screwdrivers
- Allen keys
- Wire strippers
- Pliers and crimping tools
- Multimeter
- Spirit level
- Safety goggles
Clearance Requirements
Adequate airflow must be maintained around the inverter. Minimum required clearance:
- 400 mm left and right
- 400 mm top
- 600 mm bottom
See page 6 of the manual for the clearance illustration.
Connections Overview
Connection locations include PV input terminals, AC supply terminals, RS485 ports,
LAN, CT, meter, CAN, DRM, and external WiFi/4G USB module.
Communication Connections
The inverter supports multiple communication interfaces using DIP switch selection,
including RS485 for meters/EMS, CT input, CAN-based BMS, parallel ports, and digital
inputs/outputs. Detailed pin assignments are listed on page 7.
AC Utility Grid Connection
Cable size and overcurrent protection requirements vary by model:
| Model | Max Output | Breaker | Min Cable Size |
|---|
| 3.6 kW | 16 A | C20 | 4 mm² |
| 5.0 kW | 21.7 A | C25/C32 | 6 mm² |
| 6.0 kW | 26 A | C32 | 6 mm² |
Reference: AC grid connection table on page 7.
Connecting the MID-Approved Meter
A MID-approved meter must be installed to ensure accurate monitoring and battery-charge
decisions. The CT clamp must be installed on the incoming live supply with the arrow facing
towards the property (direction of import).
Start-Up Procedure
- Close the AC circuit breaker and verify that grid readings match the MID meter.
- Turn on the DC switch.
- The inverter will start automatically when PV voltage exceeds 90 V.
- Confirm the inverter operating status.
Shutdown Procedure
- Turn off the PV switch.
- Turn off the DC switch.
- Open the AC circuit breaker.
- Wait until all LEDs are off before performing any work.
Grounding Requirements
- Protective earth must be connected before any other wiring.
- The system must not operate without grounding.
Commissioning
All systems must be commissioned using the GivEnergy online portal. Login with your
engineer credentials at: portal.givenergy.cloud. Without commissioning, the system will
not function correctly.
Decommissioning
- Follow the shutdown procedure.
- Disconnect all cabling.
- Remove locking screws and lift the inverter off the bracket.
- Remove the wall bracket.
Storage and Packaging
- Store between -25°C and +60°C.
- Retain original packaging where possible.
- Do not stack more than four units.
Warranty
The Generation 3 String Inverter range carries a 12-year manufacturer warranty.
Related Articles
AC Coupled Inverter Installation Manual
Download Manual This manual summarises the installation manual for the GivEnergy AC Coupled Inverter. It applies to the AC 3.0 (UK) model and provides an overview of installation requirements, safety information, electrical connections, ...
Hybrid Inverter 3.6 kW & 5 kW (Gen 3) Installation Manual
Download Manual This manual provides the installation, wiring, configuration, and safety guidance for the GivEnergy Gen 3 Hybrid Inverters in 3.6 kW and 5 kW models. It summarises the full installation manual and includes all required steps for ...
All in One 2 & Gateway 2 Manual
Download Manual This article provides a complete installation, safety, configuration, and maintenance summary for the GivEnergy All in One 2 (AIO2), including the MPPT Unit, Gateway 2, and Expansion Battery. It condenses all key information from the ...
Hybrid Inverter 3.6 kW & 5.0 kW (Gen 1) Installation Manual
Download Manual This manual provides a full installation and configuration summary for the GivEnergy Generation 1 Hybrid Inverter in 3.6 kW and 5.0 kW models. It consolidates all essential information from the official installation manual, including ...
Hybrid Inverter 8 kW & 10 kW (Gen 3) Installation Manual
Download Manual This manual summarises the installation manual for the GivEnergy Gen 3 Hybrid Inverter range in 8 kW and 10 kW variants. It includes wiring rules, mounting instructions, safety guidance, communication setup, and commissioning steps. ...