Hybrid Inverter 3.6 kW & 5 kW (Gen 3) Installation Manual

Hybrid Inverter 3.6 kW & 5 kW (Gen 3) Installation Manual

Download Manual

This manual provides the installation, wiring, configuration, and safety guidance for the GivEnergy Gen 3 Hybrid Inverters in 3.6 kW and 5 kW models. It summarises the full installation manual and includes all required steps for mounting, AC/DC connection, commissioning, and safe operation.

Product Overview

The Gen 3 Hybrid Inverter combines a solar PV inverter with a battery inverter to enable solar generation, battery charging and discharging, and whole-home optimisation. The unit supports dual MPPT PV input, battery communication via CAN, and advanced monitoring through LAN, WiFi or 4G modules.

Specifications

Models3.6 kW / 5.0 kW
Dimensions600H × 480W × 230D mm
Weight32–34 kg depending on model
Max PV Voltage600 V
MPPT Trackers2
Battery TypeLiFePO₄ (GivEnergy compatible)
Operating Temperature-20°C to 60°C
Warranty12 years

Box Contents

  • Hybrid Inverter (Gen 3)
  • Mounting bracket
  • Fixings pack
  • Quick start guide & documentation

Installation Requirements

  • Installation must be performed by a GivEnergy Approved Installer.
  • Store between 5°C and 60°C before installation.
  • Do not install in direct sunlight or enclosed cabinets.
  • Ensure adequate ventilation around the heat sink.

Safety Instructions

  • High-voltage DC and AC present even when powered down.
  • Batteries must only be GivEnergy-approved LiFePO₄ storage units.
  • Incorrect polarity will cause permanent inverter damage.
  • Heat sink becomes hot during operation; avoid touching.
  • Ensure protective earth (PE) is connected before energising.

Mounting the Inverter

Mount the inverter vertically with all cable glands facing downward. Use the wall bracket provided and ensure the wall is strong enough to support over 35 kg. Minimum clearances:

  • Left: 300 mm
  • Right: 300 mm
  • Top: 300 mm
  • Bottom: 500 mm

PV Connections

The inverter includes two independent MPPT trackers with one string per tracker.

  • Max string current: 16 A
  • Max input voltage: 600 V
  • Start-up voltage: 80–100 V
  • Ensure identical panel orientation and pitch per string.

Battery Connections

Gen 3 hybrid inverters use GivEnergy high-current DC battery connectors. Battery communication uses the CAN port (BMS → Inverter).

  • Use Gen 2/Gen 3 plug-to-plug battery leads.
  • Ensure BMS DIP switch addressing is correctly set.

AC Grid Connections

ModelBreakerCable Size
3.6 kWC204 mm²
5.0 kWC326 mm²

A double-pole isolator must be installed between inverter and consumer unit.

Communication Ports

  • RS485 (for meter or EMS)
  • CT input
  • CAN (battery BMS)
  • LAN port
  • USB port (WiFi/4G dongle)

Commissioning

  1. Power the inverter with AC.
  2. Wait for the screen to initialise.
  3. Confirm CT orientation and meter readings.
  4. Register the system on portal.givenergy.cloud.
  5. Perform firmware updates if prompted.

Start-Up Procedure

  1. Close AC breaker.
  2. Turn on DC switch.
  3. Turn on PV switch.
  4. Verify inverter enters normal operation.

Shutdown Procedure

  1. Turn off PV isolator.
  2. Turn off DC switch.
  3. Open AC breaker.

Storage & Maintenance

  • Store between -20°C and 60°C.
  • Keep the heat sink free from dust accumulation.
  • Check all cable glands annually.

Warranty

The Hybrid 3.6 kW & 5 kW Gen 3 models include a 12-year warranty.



    • Related Articles

    • Hybrid Inverter 3.6 kW & 5.0 kW (Gen 1) Installation Manual

      Download Manual This manual provides a full installation and configuration summary for the GivEnergy Generation 1 Hybrid Inverter in 3.6 kW and 5.0 kW models. It consolidates all essential information from the official installation manual, including ...
    • Hybrid Inverter 8 kW & 10 kW (Gen 3) Installation Manual

      Download Manual This manual summarises the installation manual for the GivEnergy Gen 3 Hybrid Inverter range in 8 kW and 10 kW variants. It includes wiring rules, mounting instructions, safety guidance, communication setup, and commissioning steps. ...
    • String Inverter (Gen 3) Installation Manual

      Download Manual This manual provides the full installation, commissioning, and safety guidance for the GivEnergy Generation 3 String Inverter range, covering the 3.6 kW, 5.0 kW and 6.0 kW models. It summarises the official Installation Manual and ...
    • Stackable Batteries Manual

      Download Manual This article summarises the Stackable Batteries Manual, which applies to the GivEnergy Stackable Battery System. This system consists of a base module with integrated electronics and stackable battery modules that can be added to ...
    • EV Charger Manual

      Download Manual This article provides an installation, configuration, and operation summary for the GivEnergy EV Charger (7.2 kW, V2). System Overview The GivEnergy EV Charger is a Type 2, 7.2 kW (32 A) AC charger designed for residential or ...

    GivBot