This manual summarises the installation manual for the GivEnergy AC Coupled Inverter. It applies to the AC 3.0 (UK) model and provides an overview of installation requirements, safety information, electrical connections, commissioning, and operational modes. This guide is intended for GivEnergy Approved Installers and qualified electricians.

Specifications Overview

  • Rated output, efficiency, environmental tolerances
  • Dimensions, weight, and mounting requirements
  • Operating temperature range and cooling clearance

Packaging Contents

  • AC Coupled Inverter
  • Mounting bracket
  • Wire covers and fixing hardware
  • Security pins/clips

Introduction

The AC Coupled Inverter is designed for standalone energy storage applications or for pairing with renewable energy systems such as solar PV, wind, or hydro. It manages charge and discharge of the connected GivEnergy battery and can operate with or without PV generation.

Installation Requirements

  • Only GivEnergy Approved Installers may install this device.
  • Ensure adequate storage/transport conditions before installation.
  • Environmental conditions must meet the inverter’s operating specifications.
  • Maintain minimum clearances: 300mm above/below, 250mm at sides.

Safety Instructions

  • Follow all electrical safety standards and isolation procedures.
  • Do not open or modify internal components.
  • Use appropriate PPE and certified test equipment.
  • Ensure the inverter is mounted securely before cabling.

Installation Steps

  • Mount the wall bracket in a load-bearing location.
  • Hang the inverter and secure using supplied locking clips.
  • Maintain ventilation clearance as specified.
  • Route AC and DC cabling through designated wire covers.

Connection Overview

  • Battery: Connect using 16mm² (minimum) tri-rated DC cables.
  • AC Grid: Connect via appropriate breaker and RCD protection.
  • EPS Output: Connect essential loads (max 3000W) with 30mA RCD.
  • Communications: USB/Wi-Fi/GPRS modules and CAN/RS485 ports as required.

EPS (Emergency Power Supply)

  • Supports up to 3000W output for essential circuits.
  • Requires overload protection up to 20A.
  • Must be installed using approved EPS switching methods.

AC Utility Grid Connection

  • Minimum 2.5mm² AC cable recommended.
  • Breakers and RCDs must match installation load requirements.
  • An earth rod must be installed at the supply origin.

Battery Connection

  • Use 16mm² DC cables as a minimum.
  • Gen 1 batteries require a DC MCB in-line.
  • Compatible with both Gen 1 and Gen 2 GivEnergy batteries.

Commissioning

  • Log in at portal.givenergy.cloud.
  • Confirm the battery, inverter, and meter are detected.
  • Configure battery parameters and operational settings.
  • Verify meter communication and live data.

Start-Up Procedure

  • Turn on AC supply.
  • Turn on battery isolator.
  • Allow inverter to boot and synchronise with grid.

Shut-Down Procedure

  • Turn off AC isolator.
  • Turn off battery isolator.
  • Wait for inverter LEDs to fully power down.

Decommissioning

  • Isolate all AC and DC supplies.
  • Disconnect battery and communication cables.
  • Remove inverter from wall bracket.
  • Store in original packaging where possible.

Work Modes

  • Eco Mode: Prioritises renewable and stored energy for self-consumption.
  • Off-Peak Charging: Charges the battery during cheaper tariff periods.
  • Backup / Island Mode: Supplies selected circuits during grid outages via EPS.

Manufacturer Warranty

The GivEnergy AC Coupled Inverter includes a 12-year warranty when installed by an approved installer and registered correctly.

Support

For further assistance, contact the GivEnergy Support Team at support@givenergy.co.uk or call 01377 252 874.

    • Related Articles

    • Hybrid Inverter 3.6 kW & 5.0 kW (Gen 1) Installation Manual

      Download Manual This manual provides a full installation and configuration summary for the GivEnergy Generation 1 Hybrid Inverter in 3.6 kW and 5.0 kW models. It consolidates all essential information from the official installation manual, including ...
    • Hybrid Inverter 3.6 kW & 5 kW (Gen 3) Installation Manual

      Download Manual This manual provides the installation, wiring, configuration, and safety guidance for the GivEnergy Gen 3 Hybrid Inverters in 3.6 kW and 5 kW models. It summarises the full installation manual and includes all required steps for ...
    • Hybrid Inverter 8 kW & 10 kW (Gen 3) Installation Manual

      Download Manual This manual summarises the installation manual for the GivEnergy Gen 3 Hybrid Inverter range in 8 kW and 10 kW variants. It includes wiring rules, mounting instructions, safety guidance, communication setup, and commissioning steps. ...
    • Stackable Batteries Manual

      Download Manual This article summarises the Stackable Batteries Manual, which applies to the GivEnergy Stackable Battery System. This system consists of a base module with integrated electronics and stackable battery modules that can be added to ...
    • Giv-Bat 9.5 (Gen 2) Manual

      Download Manual This article summarises the Giv-Bat 9.5 (Gen 2) Manual, covering the Giv-Bat 9.5-G2 9.5 kWh LiFePO₄ battery. This Generation 2 model provides high capacity for larger home storage systems, supports parallel expansion, and integrates ...

    GivBot