GEM120CT Quick Reference

GEM120CT Quick Reference

Function

Port

Cable

Description

CT +

1

White

Connect to CT clamp white lead

CT –

2

Black

Connect to CT clamp black lead

Neutral

3

Blue/Black

Supply neutral

Live

4

Brown/Red

Supply live

RS485 –

9

Green / White

To inverter B–

RS485 +

10

Orange / White

To inverter A+

CT Clamp Rule:

Clamp around live only, arrow toward load, never extend cable.

    • Related Articles

    • Quick Setup

      Plug in and secure the dongle. Connect your device to the dongle WiFi. Go to 10.10.100.254 and log in (admin/admin). Switch to STA Mode. Scan, select your WiFi network, and enter the password. Check security settings: WPA2-PSK / AES. Restart the ...
    • GEM120CT Overview

      Every system will need at least 1 GEM120 (ID1) meter installing to monitor the import and export of the building. Every GEM120 meter needs a power supply/voltage reference point. This could be a dedicated supply from a 6A, for example. Every GEM120 ...
    • Installing Multiple GEM120CT Meters (ID1 & ID2)

      Overview Where both grid and external PV generation must be monitored, two GEM120CT meters can be installed: ID1: Grid feed measurement ID2: PV string measurement Voltage Reference Bridging Both meters share the same voltage reference for accuracy. ...
    • EM115/GEM120 Grid Meter Installation

      Arrow always points towards the load CT clamp cables must not be cut down or extended EM115/GEM120 meters come with a split core CT that has a 2m cable The communication cable for the GEM120 uses the same communication terminals as the EM115 ...
    • How to Install the GEM120CT Meter

      Overview This guide explains how to wire and mount the GEM120CT correctly to ensure accurate readings. Step-by-Step Installation Isolate power before working on the system. Mount the GEM120CT on a DIN rail in the distribution board. Connect voltage ...

    GivBot