Overview

Meters can be assigned an ID number between 1 and 8, defining their role within the system.

The ID1 meter is always the main grid meter, while ID2–ID8 are used for monitoring additional devices.

Meter Roles

ID

Function

Typical Use Case

ID1

Main grid import/export meter

Monitors total property energy flow

ID2

Secondary generation or device meter

Tracks external PV generation

ID3–ID8

Reserved for future integrations

Potential for EVs, heat pumps, etc.


Example Setup

  • ID1 (Grid): Measures total property load and grid import/export.

  • ID2 (PV String): Measures an external PV system’s generation before the inverter.

    The inverter uses both meters to optimise battery charge/discharge and overall energy balance.

Notes

  • Only ID1 communicates directly with the inverter.

  • ID2 meters are bridged to the same voltage reference as ID1 for accurate phase correlation.

  • ID2 CTs must clamp the PV inverter’s live feed, arrow pointing toward property load.


    • Related Articles

    • Installing Multiple GEM120CT Meters (ID1 & ID2)

      Overview Where both grid and external PV generation must be monitored, two GEM120CT meters can be installed: ID1: Grid feed measurement ID2: PV string measurement Voltage Reference Bridging Both meters share the same voltage reference for accuracy. ...
    • Programming the GEM630MCT Meter from ID1 to ID2

      Overview Meters can be configured with IDs 1–8. ID 1 monitors the main grid; ID 2 monitors an external PV inverter or device. Steps to Change ID Press and hold ENTER until the password screen appears. Enter password 1000 using arrow buttons ▲ ▼ to ...
    • GEM120CT Overview

      Every system will need at least 1 GEM120 (ID1) meter installing to monitor the import and export of the building. Every GEM120 meter needs a power supply/voltage reference point. This could be a dedicated supply from a 6A, for example. Every GEM120 ...
    • Plant Operation

      Supported inverters Currently, system can support AC Coupled inverters (single phase) only on Firmware. D0.291-A0.282 Plant operation Plant EMS can support 3 AC Couple inverters and 6 EM115 meters in total. In discharge time, EMS can control all ...
    • Connecting GEM630MCT to a GivEnergy Inverter

      Overview The GEM630MCT communicates with the inverter through an RS485 Modbus link to relay metering data. RS485 Communication Wiring Connection GEM630MCT Port Inverter Port Cable Example RS485 + TXA+ (14) 485A (+) Orange / White RS485 – TXB– (13) ...

    GivBot