Before installing the Giv-Gateway, make sure that the whole house is isolated from the main supply.
Once isolated, please test to ensure that no voltage is present to the property before disconnecting the main supply cable from the main distribution/switch board. The Giv-Gateway should be installed between the customer’s supply meter and the switch board.
The system is IP58 rated and is safe to be installed externally. It is to install the system under a canopy, to provide additional, robust protection from sun, snow and debris.
The system must be installed in an easily accessible location, the status display must be visible and not obstructed.
Please ensure that the wall to be mounted on is sufficient enough to hold the weight of the Giv-Gateway and All-in-One.
The system must be installed in a well ventilated area and on a face with minimal sun exposure. The ambient temperature should be below 40ºC to ensure optimal operation.
The system must be installed vertically with connections always positioned at the bottom, never install horizontally, and avoid tilting the unit.
There must be adequate clearance around the Giv-Gateway. The diagram below illustrates the space required around the system.
Step 1: Place the wall mounting bracket horizontally onto the wall and mark the position of the bracket holes. Drill 2 holes at the marked positions, at least 75mm deep.
Step 2: Fix the mounting bracket to the wall using the fixings provided, or other suitable fixings.
Step 3: Fix the Giv-Gateway to the mounting bracket and secure with the fixings provided. Ensure there is adequate clearance space.