This manual summarises the installation requirements and wiring configuration for the GEM630 / SDM630MCT 3-Phase Meter. It is used to measure import/export power on three-phase GivEnergy systems.

System Overview

The GEM630 is a three-phase CT-based energy meter used to provide accurate grid import/export data to GivEnergy inverters. It is required on all three-phase systems for correct power flow control and export limiting.

Key Features

  • Supports 3-phase installations.
  • Uses split-core CT clamps (2 m cable each).
  • Provides real-time energy import/export measurement.
  • Communicates over RS485 using twisted pair.
  • Configurable as ID1 for grid metering.

Installation Requirements

  • Must be installed on the building’s main incoming supply to monitor all loads.
  • Requires a 230 V power supply and voltage reference.
  • Requires one twisted-pair RS485 communication cable back to inverter.
  • CT clamps must not be cut, extended, or modified.
  • Arrow on CT clamps must point towards the load.

Wiring Overview

The GEM630 connection pins are:

  • Pin 1: Neutral
  • Pin 2 / 3: Meter Power Live (230 V)
  • Pin 4–6: L1, L2, L3 Voltage inputs
  • Pin 13: RS485 B (-ve)
  • Pin 14: RS485 A (+ve)
  • Pin 15–20: CT inputs for L1, L2, L3 (white/black pairs)

Communication

  • RS485 A → Inverter TX+
  • RS485 B → Inverter TX-
  • Use twisted-pair cable such as Cat5/6.
  • Meters must be set to ID1 for 3-phase grid measurement.

Important Notes

  • Every 3-phase GivEnergy system requires one GEM630 (ID1).
  • A dedicated 6 A supply may be used to power the meter.
  • Incorrect CT orientation will cause reversed readings.